Installation of tanks
Installation of tanks is going well and a team from Akva Group is in charge of the installation.These tanks are in the startfeed in RAS1, but the fry will be placed in these tanks after hatching.There are 6 tanks in RAS1 and each one is 5 m. in diameter. Click on...
Precast slabs for the hatchery
Last week we lifted up precast slabs from Einingarverksmiðja in Hafnarfjörður. For the project, we received the largest crane in the Iceland from JÁ Verk and ÁB Lyftingar. Each precast slab is 22 meters long and weighs 26 tonnes.The project went well and safely....
Visit of the minister of infrastructure, members of the constituency and municipal representatives
Yesterday, representatives of LAXEY presented the project to the Minister of Infrastructure, members of parliament and town representatives of Westman Islands. Hallgrímur Steinsson and Daði Pálsson from LAXEY reviewed everything related to the project at the meeting....